Sewage treatment plant installations guide
Installation at a Glance
Before installation
- Installation should only be undertaken by a qualified specialist with appropriate professional indemnity insurance.
- Complete a proper site assessment before installation, including:
- Soil/ground conditions.
- Groundwater level.
- Flood risk.
- Existing and proposed ground levels.
- Drain invert levels.
- Potential additional/superimposed loads.
- Obtain the necessary Building Control and environmental approvals before installation.
- Confirm the HydroClear model and check all components against the delivery note.
- Determine whether the site is a dry or wet ground installation. If there is any doubt about seasonal groundwater levels, the wet-ground installation procedure must be used.
Choosing the location
- The treatment plant should be positioned at least 10 m from watercourses or other buildings, subject to site-specific requirements and approvals.
- Consider the inlet invert, drainage gradients and access for installation and future maintenance.
- Allow access for a sludge tanker, with the manual specifying a maximum hose distance of 20 m.
- Consider prevailing wind direction when choosing the location, particularly for future desludging and maintenance.
- The area around the tank should be protected from unauthorised access.
Vehicle loading & protected area
- Do not allow vehicles or other superimposed loads within 3 m of the tank.
- The protected area should be fenced off.
- If vehicle loading within this area is unavoidable, a qualified civil/structural engineer must design the installation so that loads are not transferred to the tank.
- The engineer should also sign off the installation.
Excavation & base
For a standard installation:
- Allow at least 300 mm of backfill around the tank.
- Provide a 150 mm thick concrete base beneath the tank.
- Concrete should be 25 N/mm² strength, with a 30 mm slump, and levelled to within 20 mm.
- The concrete base should extend at least 300 mm around the sides of the tank.
- Where difficult ground conditions exist, such as unstable ground or shrinking clay, allow an additional 250 mm excavation depth for hardcore and sand blinding.
- Lower the tank onto the cured concrete base and check that it is true and level.
Lifting & positioning
- Only lift the tank when it is completely empty.
- Use suitable, rated lifting equipment through the tank’s designated moulded sling slots.
- Do not use chains or wire ropes.
- Avoid sharp impacts during handling.
- Once positioned, secure or prop the tank as necessary to prevent overturning before the installation is stabilised.
Dry Ground Installation
A site is considered dry only where groundwater will not rise above the base of the tank at any time of year.
- If the surrounding ground is non-porous, such as clay or bedrock, water can collect around the tank.
- In these circumstances, provide a suitable land drain to ensure the installation remains free-draining, or use the wet-ground installation procedure.
- After positioning the tank, fill it to approximately 600 mm water depth.
- The Reactor/Media Chamber must be filled first to prevent buoyancy damage.
- Keep the liquid level in the reactor higher than the settlement chambers.
- Carefully consolidate concrete beneath the lower radii of the tank.
- Do not use a vibrating poker.
- Continue filling the tank while simultaneously backfilling with 12–15 mm washed, clean, chemically inert pea gravel/free of sharp edges.
- Maintain the water level approximately 200 mm above the external backfill level.
- Once filled to inlet/outlet height, connect the pipes and continue backfilling to approximately 100 mm above the tank body.
Wet Ground Installation
- Treat the site as wet ground if groundwater can rise above the base of the tank.
- If you are unsure of the groundwater level, use the wet-ground installation method.
- The maximum permissible water table is 1.7 m from the base of the tank.
- Provide suitable pumping equipment to keep the excavation free of groundwater during installation.
- Poor ground conditions may require planking, strutting and temporary shuttering.
- Allow at least:
- 150 mm concrete below the tank
- 300 mm concrete around the tank
- Lower the tank onto the cured concrete base and fill with water as specified.
- Place and consolidate concrete carefully around the tank, ensuring no voids remain.
- Do not use a vibrating poker.
- Maintain the water level approximately 400 mm higher than the external concrete level.
- Fill the tank to outlet-pipe height and bring the concrete to within approximately 400 mm of this level.
- Allow the concrete to harden for approximately 24 hours before continuing the installation.
- Once hardened, connect the inlet/outlet pipes and continue the concrete backfill, covering the top of the tank body with approximately 100 mm of concrete.
Pipework
- The recommended inlet gradient from the dwelling to the treatment plant is 1:40.
- 1:80 may be acceptable with Building Control approval.
- For gravity outlet versions, the outlet gradient should be approximately 1:80 minimum, subject to the specific installation design.
- If pipes are too shallow or pass beneath walls/foundations, they should be suitably protected.
- Ensure all pipework is correctly supported and free from obstructions before commissioning.
Blower & Electrical Installation
- The standard system requires a single-phase 240 V supply.
- Use a suitable 3-core steel-wire-armoured (SWA) cable.
- Provide a dedicated circuit with appropriate isolation and protection.
- The incoming supply must have a separate earth-leakage circuit breaker at the source building.
- The SWA cable must be correctly installed and the steel armour earthed at both ends.
- Electrical work must only be completed by a fully qualified electrician.
- Position the external blower housing at ground level close enough to the tank for the supplied airline to reach.
- Remove the perforated transport straps securing the compressor before operation.
- Keep the blower housing protected from direct sunlight where possible, as excessive heat can reduce diaphragm life.
- Keep the blower housing closed while operating.
Airline connection
- Feed the supplied airline through the blower housing gland.
- Connect it securely to the air blower using the supplied fittings and jubilee clip.
- Connect the other end to the airline connection on the tank.
- Route the required pipework/cables through the 110 mm service duct.
- Check all airline connections are airtight before commissioning.
Important tips:
- Installation must be carried out by a qualified specialist.
- Establish whether the site is dry or wet ground before installation. If in doubt, use the wet-ground procedure.
- Never lift the tank when it contains water.
- Do not use chains or wire ropes for lifting.
- Keep vehicles and other superimposed loads at least 3 m from the tank, unless a structural engineer has designed and signed off the installation.
- Provide a 150 mm concrete base and 300 mm minimum concrete/backfill around the tank, as applicable to the installation method.
- Do not use a vibrating poker around the tank.
- During dry-ground installation, maintain the tank water level approximately 200 mm above the backfill level.
- During wet-ground installation, maintain the water level approximately 400 mm above the concrete backfill level.
- For dry installations, fill the Reactor/Media Chamber first and keep its water level higher than the settlement chambers.
- Use only the specified 12–15 mm clean, washed pea gravel where pea-gravel backfill is required.
- Allow the wet-ground concrete to harden for approximately 24 hours before continuing the backfill.
- Electrical installation must be completed by a qualified electrician.
- The blower housing contains 240 V electrical equipment and must be isolated before maintenance.
- Never enter the treatment tank. Wastewater treatment can produce hazardous gases even when the tank is drained