Sewage treatment plant installations guide

Installation at a Glance

Before installation

  • Installation should only be undertaken by a qualified specialist with appropriate professional indemnity insurance.
  • Complete a proper site assessment before installation, including:
    • Soil/ground conditions.
    • Groundwater level.
    • Flood risk.
    • Existing and proposed ground levels.
    • Drain invert levels.
    • Potential additional/superimposed loads.
  • Obtain the necessary Building Control and environmental approvals before installation.
  • Confirm the HydroClear model and check all components against the delivery note.
  • Determine whether the site is a dry or wet ground installation. If there is any doubt about seasonal groundwater levels, the wet-ground installation procedure must be used.

Choosing the location

  • The treatment plant should be positioned at least 10 m from watercourses or other buildings, subject to site-specific requirements and approvals.
  • Consider the inlet invert, drainage gradients and access for installation and future maintenance.
  • Allow access for a sludge tanker, with the manual specifying a maximum hose distance of 20 m.
  • Consider prevailing wind direction when choosing the location, particularly for future desludging and maintenance.
  • The area around the tank should be protected from unauthorised access.

Vehicle loading & protected area

  • Do not allow vehicles or other superimposed loads within 3 m of the tank.
  • The protected area should be fenced off.
  • If vehicle loading within this area is unavoidable, a qualified civil/structural engineer must design the installation so that loads are not transferred to the tank.
  • The engineer should also sign off the installation.

Excavation & base

For a standard installation:

  • Allow at least 300 mm of backfill around the tank.
  • Provide a 150 mm thick concrete base beneath the tank.
  • Concrete should be 25 N/mm² strength, with a 30 mm slump, and levelled to within 20 mm.
  • The concrete base should extend at least 300 mm around the sides of the tank.
  • Where difficult ground conditions exist, such as unstable ground or shrinking clay, allow an additional 250 mm excavation depth for hardcore and sand blinding.
  • Lower the tank onto the cured concrete base and check that it is true and level.

Lifting & positioning

  • Only lift the tank when it is completely empty.
  • Use suitable, rated lifting equipment through the tank’s designated moulded sling slots.
  • Do not use chains or wire ropes.
  • Avoid sharp impacts during handling.
  • Once positioned, secure or prop the tank as necessary to prevent overturning before the installation is stabilised.

Dry Ground Installation

A site is considered dry only where groundwater will not rise above the base of the tank at any time of year.

  • If the surrounding ground is non-porous, such as clay or bedrock, water can collect around the tank.
  • In these circumstances, provide a suitable land drain to ensure the installation remains free-draining, or use the wet-ground installation procedure.
  • After positioning the tank, fill it to approximately 600 mm water depth.
  • The Reactor/Media Chamber must be filled first to prevent buoyancy damage.
  • Keep the liquid level in the reactor higher than the settlement chambers.
  • Carefully consolidate concrete beneath the lower radii of the tank.
  • Do not use a vibrating poker.
  • Continue filling the tank while simultaneously backfilling with 12–15 mm washed, clean, chemically inert pea gravel/free of sharp edges.
  • Maintain the water level approximately 200 mm above the external backfill level.
  • Once filled to inlet/outlet height, connect the pipes and continue backfilling to approximately 100 mm above the tank body.

Wet Ground Installation

  • Treat the site as wet ground if groundwater can rise above the base of the tank.
  • If you are unsure of the groundwater level, use the wet-ground installation method.
  • The maximum permissible water table is 1.7 m from the base of the tank.
  • Provide suitable pumping equipment to keep the excavation free of groundwater during installation.
  • Poor ground conditions may require planking, strutting and temporary shuttering.
  • Allow at least:
    • 150 mm concrete below the tank
    • 300 mm concrete around the tank
  • Lower the tank onto the cured concrete base and fill with water as specified.
  • Place and consolidate concrete carefully around the tank, ensuring no voids remain.
  • Do not use a vibrating poker.
  • Maintain the water level approximately 400 mm higher than the external concrete level.
  • Fill the tank to outlet-pipe height and bring the concrete to within approximately 400 mm of this level.
  • Allow the concrete to harden for approximately 24 hours before continuing the installation.
  • Once hardened, connect the inlet/outlet pipes and continue the concrete backfill, covering the top of the tank body with approximately 100 mm of concrete.

Pipework

  • The recommended inlet gradient from the dwelling to the treatment plant is 1:40.
  • 1:80 may be acceptable with Building Control approval.
  • For gravity outlet versions, the outlet gradient should be approximately 1:80 minimum, subject to the specific installation design.
  • If pipes are too shallow or pass beneath walls/foundations, they should be suitably protected.
  • Ensure all pipework is correctly supported and free from obstructions before commissioning.

Blower & Electrical Installation

  • The standard system requires a single-phase 240 V supply.
  • Use a suitable 3-core steel-wire-armoured (SWA) cable.
  • Provide a dedicated circuit with appropriate isolation and protection.
  • The incoming supply must have a separate earth-leakage circuit breaker at the source building.
  • The SWA cable must be correctly installed and the steel armour earthed at both ends.
  • Electrical work must only be completed by a fully qualified electrician.
  • Position the external blower housing at ground level close enough to the tank for the supplied airline to reach.
  • Remove the perforated transport straps securing the compressor before operation.
  • Keep the blower housing protected from direct sunlight where possible, as excessive heat can reduce diaphragm life.
  • Keep the blower housing closed while operating.

Airline connection

  • Feed the supplied airline through the blower housing gland.
  • Connect it securely to the air blower using the supplied fittings and jubilee clip.
  • Connect the other end to the airline connection on the tank.
  • Route the required pipework/cables through the 110 mm service duct.
  • Check all airline connections are airtight before commissioning.

 

Important tips:

  • Installation must be carried out by a qualified specialist.
  • Establish whether the site is dry or wet ground before installation. If in doubt, use the wet-ground procedure.
  • Never lift the tank when it contains water.
  • Do not use chains or wire ropes for lifting.
  • Keep vehicles and other superimposed loads at least 3 m from the tank, unless a structural engineer has designed and signed off the installation.
  • Provide a 150 mm concrete base and 300 mm minimum concrete/backfill around the tank, as applicable to the installation method.
  • Do not use a vibrating poker around the tank.
  • During dry-ground installation, maintain the tank water level approximately 200 mm above the backfill level.
  • During wet-ground installation, maintain the water level approximately 400 mm above the concrete backfill level.
  • For dry installations, fill the Reactor/Media Chamber first and keep its water level higher than the settlement chambers.
  • Use only the specified 12–15 mm clean, washed pea gravel where pea-gravel backfill is required.
  • Allow the wet-ground concrete to harden for approximately 24 hours before continuing the backfill.
  • Electrical installation must be completed by a qualified electrician.
  • The blower housing contains 240 V electrical equipment and must be isolated before maintenance.
  • Never enter the treatment tank. Wastewater treatment can produce hazardous gases even when the tank is drained